DescriptionMod. No. 8 - ARCHITECTURAL/ENGINEERING SERVICES FOR METROPOLITAN POLICE DEPARTMENT (MPD) AND DEPARTMENT OF CORRECTIONS (DOC) MOVE TO ONE JUDICIARY SQUARE
SupplierDLR Group of DC P.C.
TO
MOD8
Procurement MethodModification
Performance
Start Date08-09-2021
Performance
End Date09-30-2025
DGS DivisionContracts and Procurement
[-]less...
07-17-2025
Contract#DCAM-22-CS-RFP-0020
Contract $$3,559,797.38
[+]more...
DescriptionMod. No. 2 - Design-Build Services for DOC Central Boiler Plant (Definitized Contract)
SupplierGCS, Inc
TO
MOD2
Procurement MethodModification
Performance
Start Date05-09-2024
Performance
End Date12-24-2025
DGS DivisionCapital Construction
[-]less...
07-02-2025
Contract#DCAM-25-CS-RFP-0001
Contract $$3,403,056.74
[+]more...
DescriptionDesign-Build Services for KC Lewis Swing Space to Support Seaton Elementary School Modernization
SupplierAtmos Solutions Inc
TO
MOD
Procurement MethodRFP
Performance
Start Date07-02-2025
Performance
End Date12-14-2026
DGS DivisionCapital Construction
[-]less...
06-27-2025
Contract#DCAM-23-CS-RFP-0037
Contract $$62,026,540.00
[+]more...
DescriptionDesign-Build Services for New Fort Davis Community Center Building (Definitized Contract)
SupplierBSC-CWC New Fort Davis JV LLC
TO
MOD
Procurement MethodRFP
Performance
Start Date06-27-2025
Performance
End Date04-19-2027
DGS DivisionCapital Construction
[-]less...
06-25-2025
Contract#DCAM-22-CS-RFP-0002
Contract $$40,247,334.00
[+]more...
DescriptionConstruction Management At-Risk Services Fort Lincoln Park and New Recreation and Early Childhood Education Center (Definitized Contract)
SupplierMCN Build, Inc.
TO
MOD
Procurement MethodRFP
Performance
Start Date06-25-2025
Performance
End Date12-28-2026
DGS DivisionCapital Construction
[-]less...
06-23-2025
Contract#DCAM-22-CS-RFQ-0016X
Contract $$1,745,474.00
[+]more...
DescriptionMod. No. 1 - Flooring Replacement at Brightwood, Cleveland, Langdon, and Simon Elementary Schools & Stuart Hobson Middle School
SupplierB&B Solutions US, LLC
TO2
MOD1
Procurement MethodModification
Performance
Start Date03-05-2025
Performance
End Date12-30-2025
DGS DivisionCapital Construction
[-]less...
06-20-2025
Contract#DCAM-25-CS-SS-0005
Contract $$235,982.00
[+]more...
DescriptionArchitectural and Engineering Services for the Office of Neighborhood Safety and
Engagement (ONSE) Building
SupplierEmotive Architecture
TO
MOD
Procurement MethodSole Source
Performance
Start Date06-20-2025
Performance
End Date05-31-2026
DGS DivisionCapital Construction
[-]less...
06-20-2025
Contract#DCAM-24-CS-RFP-0001
Contract $$11,850,674.00
[+]more...
DescriptionMod. No. 2 - DESIGN-BUILD AGREEMENT FOR MEYER ELEMENTARY SCHOOL HVAC UPGRADES (GMP)
SupplierChiaramonte Construction Co.
TO
MOD2
Procurement MethodModification
Performance
Start Date06-25-2024
Performance
End Date06-15-2027
DGS DivisionCapital Construction
[-]less...
05-28-2025
Contract#DCAM-23-CS-RFP-0029
Contract $$3,062,916.00
[+]more...
DescriptionDesign-Build Services for Upshur Recreation Center Modernization (Definitized Contract)
SupplierKadcon Corporation
TO
MOD
Procurement MethodRFP
Performance
Start Date05-28-2025
Performance
End Date01-27-2027
DGS DivisionCapital Construction
[-]less...
05-28-2025
Contract#DCAM-20-CS-RFQ-0001A
Contract $$0.00
[+]more...
DescriptionMod. No. 1 - DESIGN-BUILD SERVICES FOR DUKE ELLINGTON PARK PHASE II
SupplierH.E.P. Construction, Inc.
TO19
MOD1
Procurement MethodTask Order
Performance
Start Date04-25-2024
Performance
End Date08-29-2025
DGS DivisionCapital Construction
[-]less...
05-27-2025
Contract#DCAM-23-CS-IFB-0003
Contract $$2,549,170.00
[+]more...
DescriptionConstruction Services for MBB Exterior Stabilization for 9th Floor Terrace and Windows
SupplierWinmar, Inc.
TO
MOD
Procurement MethodIFB
Performance
Start Date05-27-2025
Performance
End Date08-01-2026
DGS DivisionCapital Construction
[-]less...
05-27-2025
Contract#DCAM-20-CS-RFQ-0001AI
Contract $$0.00
[+]more...
DescriptionMod. No. 4 - Design-Build Services for Sherwood Recreation Center Exterior Improvements (No-Cost Time Extension)
SupplierSPD Contracting Inc.
TO2
MOD4
Procurement MethodModification
Performance
Start Date04-09-2024
Performance
End Date08-29-2025
DGS DivisionCapital Construction
[-]less...
05-23-2025
Contract#DCAM-22-CS-RFP-0002
Contract $$0.00
[+]more...
DescriptionMod. No. 9 - Construction Management At-Risk Services Fort Lincoln Park and New Recreation and Early Childhood Education Center (NTE & Letter Contract)
SupplierMCN Build, Inc.
TO
MOD9
Procurement MethodModification
Performance
Start Date11-20-2022
Performance
End Date06-30-2025
DGS DivisionCapital Construction
[-]less...
05-20-2025
Contract#DCAM-24-CS-RFP-0024
Contract $$0.00
[+]more...
DescriptionMod. No. 1 - Construction Management At-Risk Services for the Modernization of the Jelleff Recreation Center (No-Cost Time Extension)
SupplierMCB
TO
MOD1
Procurement MethodModification
Performance
Start Date12-04-2024
Performance
End Date07-11-2025
DGS DivisionCapital Construction
[-]less...
05-16-2025
Contract#DCAM-25-CS-RFP-0002
Contract $$995,000.00
[+]more...
DescriptionDESIGN-BUILD AGREEMENT FOR SEATON ELEMENTARY SCHOOL MODERNIZATION (NTP & Letter Contract)
SupplierGCS, Inc. dba GCS-SIGAL
TO
MOD
Procurement MethodRFP
Performance
Start Date05-16-2025
Performance
End Date10-30-2025
DGS DivisionCapital Construction
[-]less...
05-14-2025
Contract#DCAM-25-CS-RFP-0004
Contract $$995,000.00
[+]more...
DescriptionDESIGN-BUILD SERVICES FOR KETCHAM ELEMENTARY SCHOOL MODERNIZATION
SupplierChiaramonte Construction Co. dba CC Co.
TO
MOD
Procurement MethodRFP
Performance
Start Date05-14-2025
Performance
End Date11-14-2025
DGS DivisionCapital Construction
[-]less...
04-30-2025
Contract#DCAM-24-CS-RFP-0035
Contract $$7,951,133.00
[+]more...
DescriptionDESIGN-BUILD AGREEMENT FOR BURRVILLE ELEMENTARY SCHOOL MODERNIZATION
SupplierGCS, Inc. dba GCS-SIGAL
TO
MOD
Procurement MethodRFP
Performance
Start Date04-30-2025
Performance
End Date01-17-2029
DGS DivisionCapital Construction
[-]less...
04-30-2025
Contract#DCAM-22-CS-RFP-0009
Contract $$17,859,313.29
[+]more...
DescriptionMod. No. 4 - Design Build Services for Stoddert Elementary School Classroom Addition (GMP)
SupplierChiaramonte Construction Co. dba CC Co.
TO
MOD4
Procurement MethodModification
Performance
Start Date05-16-2023
Performance
End Date07-25-2025
DGS DivisionCapital Construction
[-]less...
04-25-2025
Contract#DCAM-25-CS-RFP-0001
Contract $$995,000.00
[+]more...
DescriptionDesign-Build Services for KC Lewis Swing Space to Support Seaton Elementary School Modernization (NTP & Letter Contract)
SupplierAtmos Solutions Inc
TO
MOD
Procurement MethodRFP
Performance
Start Date04-25-2025
Performance
End Date10-31-2025
DGS DivisionCapital Construction
[-]less...
04-11-2025
Contract#DCAM-24-CS-RFP-0032
Contract $$995,000.00
[+]more...
DescriptionDESIGN-BUILD SERVICES FOR CHISHOM ELEMENTARY SCHOOL (FORMERLY TYLER ELEMENTARY SCHOOL) MODERNIZATION (NTP & Letter Contract)
SupplierMCN Build, Inc.
TO
MOD
Procurement MethodRFP
Performance
Start Date04-11-2025
Performance
End Date09-30-2025
DGS DivisionCapital Construction
[-]less...
04-11-2025
Contract#DCAM-24-CS-RFP-0002
Contract $$0.00
[+]more...
DescriptionMod. No. 3 - Design-Build Services for Kenilworth Elementary School HVAC Upgrades (NTP & Letter Contract )
SupplierBlue Skye Construction, LLC
TO
MOD3
Procurement MethodModification
Performance
Start Date08-06-2024
Performance
End Date06-30-2025
DGS DivisionCapital Construction
[-]less...
04-10-2025
Contract#DCAM-23-CS-RFP-0017
Contract $$65,858,204.00
[+]more...
DescriptionMod. No. 1 - Design-Build Services for MacArthur High School Expansion (ESA 2)
SupplierMCN Build, Inc.
TO
MOD1
Procurement MethodModification
Performance
Start Date06-26-2024
Performance
End Date01-15-2027
DGS DivisionCapital Construction
[-]less...
04-09-2025
Contract#DCAM-22-CS-RFQ-0001M
Contract $$284,263.78
[+]more...
DescriptionMod. No. 3 - Renovation Madison Shelter (“Project”)
SupplierProtec Construction Inc.
TO7
MOD3
Procurement MethodModification
Performance
Start Date04-09-2025
Performance
End Date08-29-2025
DGS DivisionCapital Construction
[-]less...
04-07-2025
Contract#DCAM-25-CS-SS-0002
Contract $$699,721.00
[+]more...
DescriptionMarie Reed Elementary School Playground Improvements